In anticipation of the Centenial Celebration of Post #147 on March 21, 2021, we have embarked on an ambitious plan to both expand our programs and renovate our building. You can make a donation to our Building Renovation Fund here.
Download the summary of the Renovation Plan
Updates on the Plan implementation will be posted below.
11/3/13:
Restroom Accessibility Upgrade: We have completed the second preliminary review of our plans with the City of Clovis and are ready to submit them with the permit application. We will submit the application and plans to the City of Clovis the first week of December. During the next couple of months we will be selecting all of the items for the restrooms such as tile and fixtures, so that when we go out to bid all of the contractors will have the same information to bid on. Sometime in February 2014 we plan on going out to bid to no less than three contractors. As of now the start date will be June 16th 2014. The post will be dark at that time and installation of new officers will have been completed.